Custom Search
Temp
 
Home --> Archives --> Electrical --> Installing A Sub-Panel: Overview
Do-it-yourself sub-panel for more electrical circuits.

Updating Old House Wiring:

Adding A Sub-Panel - An Overview

A Subsidiary Panel On The Second Floor Becomes A Branching-Off Point For Nearby Circuits

 
In This Article:

A brief summary of the major steps involved in adding a subsidiary breaker panel to an existing main breaker box.

Related Articles:
Skill Level:
3+ (Intermediate and Higher)
Time Taken:
About 6 Hours
Author:
, Editor
Project Date:
March 2006
 
 
Start >>

 

[See Tools and Materials] [Add your comments below the article]

Why Use A Sub-Panel?

In a small house, it's easy and inexpensive to place a main breaker panel in the basement, garage  or hallway, and then run wires to each part of the house for the individual circuits.

In larger houses (and most commercial buildings), it's common to have a high-capacity main breaker panel that supplies power to several subsidiary electrical panels (commonly called sub-panels) located closer to the individual circuits.

The concept is simple: A big fat wire feeds the main panel, and several not-so-fat wires feed the sub-panels, which supply power to their local circuits. This technique saves labor and materials because the wires for each circuit don't need to be routed across the building to the main panel.

Also, a sub-panel can be placed adjacent to the main panel as a way to add more circuit breakers to a main panel that has no room for more breakers.

 

New Sub-Panel - A Quick Do-It-Yourself Summary:

  1. Route the sub-feed cable from the main panel to the new sub-panel. BUT... size matters, and length matters too. See below for more info.
  2. Mount the sub-panel, either surface mounted to plywood, or flush mounted between the studs.
  3. Connect the sub-feed to the sub-panel lugs.
  4. Connect the sub-feed to the appropriate 2-pole breaker in the main panel.
  5. Connect the branch circuits to the sub-panel.
  6. Test everything, call for "rough" electrical inspection.
  7. Install wallboard, then complete the finish electrical work as needed.
  8. Get the electrical finish work inspected.

 

About This Project:

I have some friends who own a century-old house, and for the past five years I've been helping them remodel the place from top to bottom. When the wall and ceiling plaster was removed, we took the time to replace the old knob-and-tube wiring.

Many years ago (the 1950's or early 60's) the house had been divided into two apartments, and the wiring was partially updated at that time. A subsidiary panel was installed on the second-floor to service the upstairs apartment. This remote breaker box was fed with a 6-3 cable (that's 3 conductors, each a Number 6 size) with no ground wire.

The sub-panel had been installed in an old attic, but the attic had been converted to a bedroom. The room had no closet, and the previous homeowner installed closet rods above the sub-panel, so the panel was blocked by hanging clothes. The National Electrical Code requires a 3' x 3' clear area in front of a panel, so this arrangement was a code violation, albeit a minor one.

We decided to solve several problems by simply replacing the old sub-panel with a new sub-panel of the same capacity, and then re-wiring all of the existing circuits. The new sub-panel would be located in a hallway instead of a bedroom. Perhaps the trickiest part of installing a new sub-panel in an old house is running the sub-feed cable from the main panel to the sub-panel. Since we had stripped the ceiling and walls below, we were able to easily run a new 6-3G cable from the basement to the second-floor hallway.

 

Size Matters:

Sub-Panel:

There are two main factors to sub-panel size:

  • The number of available slots for circuit breakers.
  • The amperage capacity (ampacity) of the conductive parts within the panel.

We used a 125 Amp capacity panel with spaces for 20 breakers, but we did not use the full amperage capacity.

Sub-Feed:

The size of the conductors (individual wires) inside a sub-feed cable dictates how much current (measured in Amps) can flow through that cable. We used 6-3G cable, which is normally capable of handling 50 Amps. But... there is a maximum length to that cable, 55 feet, before there is a possible problem of a voltage drop happening.

Sub-Feed Breaker:

As with all electrical wiring, the circuit breaker amperage capacity must be equal to or less than the ampacity of the cable that it serves. We used a 50 Amp 2-pole breaker.

 

Running The Sub-Feed Cable:

The logical question is: Why not route the new sub-feed cable in the exact location of the original cable?

The original cable ran on the outside of an interior wall, beside a drain pipe and supply pipes for the upstairs kitchen. The entire bundle of utilities was protected with a U-shaped cover made from 1x6's. These pipes and wires interfered with our main-floor kitchen remodeling project, so when the walls were opened up we routed the new sub-feed cable through the wall cavity, where it belongs.

I didn't get a chance to shoot any pictures of running this cable. Some important points are:

  1. The cable needs to be secured to the framing every 4 feet, or closer.
  2. When the cable needs to run through a joist or stud, the cable needs to be placed far enough back from the face so that a nail or screw won't accidentally puncture the insulation. I believe the rule is to place the cable at least 1-1/4" behind the face, or apply a metal protective plate to the face of the stud.
  3. When holes are drilled through framing members, the holes need to be located in regions that will not weaken the structure. This typically means that holes need to be drilled in the middle third of a joist, as measured vertically.

 

Mounting The Sub-Panel:

Mounting a sub-panel to wall studs.

After cutting a rectangular hole in the wall, we secured the sub-panel to the studs with 1¼" sheet metal screws.

 

 

After installing a 3/4" cable clamp, we inserted the sub-feed cable into the panel.

Running 6-3G sub-feed cable into an electrical sub-panel.
 

 

Connecting The Sub-Feed To The Sub-Panel Lugs:

At The Sub-Panel:

After the sub-feed cable jacket was stripped, we connected the four wires:

  1. The hot wires, red and black, were each connected to a lug on the bus bars.
  2. The neutral wire (white wire) was connected to the neutral bus bar.
  3. The ground (bare) wire was connected to the ground bus.

 

 

 

Connecting The Sub-Feed To The Supply Breaker:

At The Main Panel:

 

We ran the 6-3G sub-feed into the main breaker panel.

 

 

Inside The Main Panel:

The neutral and ground wires were connected to the neutral/ground bus bar.

 

 

The hot wires were connected to a 50 Amp 2-pole circuit breaker. The breaker was snapped into place so it connected to the hot bus bars.

Then we removed two knock-outs from the cover panel, to accommodate the new breaker.

 

 

Connecting The Branch Circuits:

At The Sub Panel:

We ran a new 14-2G cable into the panel.

 

 

After the cable jacket was cut away, we secured the ground wire in the ground bus.

Note that one screw in the ground bus is permitted to hold two or three wires.

 

 

I stripped the end of the neutral wire and connected it to the neutral bus bar.

 

 

 

The hot wire was stripped and connected to a 15 Amp circuit breaker.

 

 

The breaker was connected to the panel.

This type of breaker simply hooks onto a metal tab and pushes onto the hot bus bar.

 

 

 
 
 
 
 
 
 
 
Related Electrical Articles:
 
Most Popular Electrical Articles:
 
 
Attention:

Before you hurt yourself, read our disclaimer.

 
 

 

 

 
 

 

 

 
 

 

 

 

 
 

 

 
 

 

But Wait, There's More...

After we installed all the individual circuit breakers, we were ready for the "rough-in" electrical inspection.

Then we installed the drywall. When the wallboard was finished and painted, we finished the electrical work by installing the switches, receptacles, and light fixtures. When all the electrical work is done the electrical inspector can be called for the final electrical inspection.

 

 

HammerZone's Recommended Electrical Tools
 
 

 

Warnings And Cautions:

I strongly recommend anybody who plans on doing their own electrical work to do more research besides just reading these articles. I am not an electrician and I certainly do not know everything about wiring. I could be wrong. The electrical codes in your area may be different than in my area.

While minor electrical changes and repairs may not require a permit, larger projects usually do. Consult your local Building Department (look in the "local government" section of your phone book) before making your own major electrical changes. Local electrical inspectors usually are available during their early morning hours to answer your code questions, normally free of charge. If you've done your homework, you can speak intelligently and learn about lots of valuable rules and regulations.

Read HammerZone's disclaimer.

 

Recommended Reading:

I highly recommend the book Wiring a House (For Pros By Pros) by Rex Cauldwell, which is available on Amazon.com.

 

More Info:
Tools Used:
  • Cordless Drill/Driver
  • Reciprocating Saw
  • Heavy-Duty Drill with Auger Bits
  • Basic Carpentry Tools
Materials Used:
  • Sub-Panel, Cutler-Hammer
  • 6-3G Cable
  • Single Pole Circuit Breakers
  • 2-Pole Circuit Breaker, 50 Amp
  • Cable Clamps
 
Do you like this article ?
 
 
 
 
 
 

 

 

 

 

 

 

 

 

 
 
Custom Search